Worklog synchronization can be useful to track progress of tickets or overall project progress.
Example on the screen shows two issues that synchronize Work Logs (from left to right). - In this scenario worklogs synchronization is enabled on left contract. The entries were created in SSP-25 and replicated to SC-1.
- Worklog created by "Administrator" user is synchronized using "Technical User". It has to have Worklog Permission in that project.
This is because User Directories often differ between two synchronized JIRAs.- However, you got information about username / connection /contract / time of original worklog in the description.
- Worklogs are ordered chronological based on reported time in worklog entry (not time when user added a worklog).
- Worklog marked with red border is not synchronized because worklog synchronization was not yet enabled.
- Workflogs are synchronized incremental - changes to worklogs are not propagated to the remote JIRA.
Additional info: (2) Contract | |
If receiving worklog is disabled in configuration then you will get follwoing status: